Monday, June 4, 2012
Week 9
This week marked the closing of our project. All work on the boat was concluded and a final report was constructed going into detail about all aspects of technical activities, construction and results. A presentation was also made which will be presented for an audience tomorrow morning.
Tuesday, May 29, 2012
Week 8
The boat was worked on a little more to get everything just right. The netting was adjusted to make the boat more secure and balance. The second pro engineer drawing of the boat was started. Testing for the lumber has yet to be completed but another ASTM was found that could provide enough information that we don't have to test it. A program was created in Maple 15 that will allow users to select quantities and weights and find out how much cargo or water bottles this can handle. This is not yet completed but will be in the week to come.
![]() |
| Figure 1: Maple 15 program |
Monday, May 21, 2012
Week 7
The construction of the boat was completed. In order to do this, the other pontoon of bottle needed to be created and the base constructed. The first step was to collect more bottles. This was done by visiting a view houses right before the recycling truck came. This did not take long due to the fact that plastic bottle were abundant.
There were some changes made during the construction that differs from the original design. The original design called for cardboard to cover the top. We did not think this would provide enough support. We attached a half inch thick piece of ply-wood instead of the cardboard. Before adding any weight we noticed that it was too rigid and starting to crack from all the weight. Two more two by fours were adding going across the base to provide spots to hold the weight of a person. With this attachment the strength of the ply-wood was not needed. We could have switched back to cardboard but left it on so we could provide more weight for testing.
The testing of the boat was held in a pool. The first attempt we applied two people to the raft. The raft held up but was very unbalanced. This was due to the bottles collected in the middle of the pontoon causing the raft to act like a seesaw. We solved this by applying rope around the middle of both pontoon forcing the bottles to travels the four edges. This balanced the boat much better. Another person was then adding to show that it can hold its goal of 450 pounds. The three people totaled almost 500 pounds. We concluded that any more weight added would cause the raft to become very unbalanced.
There were some changes made during the construction that differs from the original design. The original design called for cardboard to cover the top. We did not think this would provide enough support. We attached a half inch thick piece of ply-wood instead of the cardboard. Before adding any weight we noticed that it was too rigid and starting to crack from all the weight. Two more two by fours were adding going across the base to provide spots to hold the weight of a person. With this attachment the strength of the ply-wood was not needed. We could have switched back to cardboard but left it on so we could provide more weight for testing.
The testing of the boat was held in a pool. The first attempt we applied two people to the raft. The raft held up but was very unbalanced. This was due to the bottles collected in the middle of the pontoon causing the raft to act like a seesaw. We solved this by applying rope around the middle of both pontoon forcing the bottles to travels the four edges. This balanced the boat much better. Another person was then adding to show that it can hold its goal of 450 pounds. The three people totaled almost 500 pounds. We concluded that any more weight added would cause the raft to become very unbalanced.
![]() |
| Figure 1: The boat with the added rope around the pontoon and 2"x4"s across the base. |
![]() |
| Figure 2: Raft holding almost 500 pounds and staying afloat. |
Monday, May 14, 2012
Week 6
This week, we tested how much weight the boat could hold. A 100 pound weight was placed on the boat, and then 25 pound cinderblocks were repeatedly added to the boat, to see how much it could hold. The boat supported the 100-pound weight and six 25-pound cinder blocks, meaning the boat currently holds 250 pounds. No additional weight was added because the pool was not clean and we did not want to risk sinking the boat. Also, ATSM standards were acquired from the engineering librarian. We hope to run the lumber and plastic tests this week.
| Figure 1: Testing of the pontoon |
Monday, May 7, 2012
Week 5
This week calculations were completed. We built the first model of the boat and construction proceeded as planned. The boat was built to match the original specifications. Three hundred and ninety eight water bottles were procured and split between the two sides of the boat. The two by fours were nailed together, and the cardboard flooring was attached on top. However, the boat was not tested this week, due to time and weather concerns. We will test the boat this week to see if it can hold the 450 pounds it is required to.
Monday, April 30, 2012
Week 4
All of the materials needed for construction have been ordered and the boat is ready to assemble. Labs procedures have been created to test materials the boat is going to be made of. More calculations will be made to figure out the best possible combination of materials and dimensions for the boat. Construction will begin this week and testing of the completed boat will be done as soon as possible. We will continue to conduct research on all the materials.
Monday, April 23, 2012
Week 3
This week we decided on the design and dimensions we would be using for our boat and constructed a drawing in ProEngineer. We also researched what kind of netting we wanted to use for the sides of the boat and purchased it from the internet. We made a list of all other materials needed for the construction of the boat. We will purchase them on the day of construction. This coming week we intend to research the other materials we will be using and design tests on them to find out their properties. We will hopefully be able to start our test this week.
![]() |
| Plastic Sheeting Purchased for the Cardboard |
![]() |
| Netting to contain the water bottles |
Monday, April 16, 2012
Week 2
In week 2, we started our project overview, we finished many of the sections and assigned the others to each other to do throughout the week. We researched other boats constructed of recycled materials and we researched the need for disaster relief rafts. Please see the project design page on the side.
![]() |
| An example of a boat made from recycled material |
Monday, April 9, 2012
Week 1
In week one we decided on a project that goes along with the sustainability ideas presented in class. Our goal is to create a boat that can be made from common household items that are typically in excess. We would like to create the boat out of 100% recycled material such as cardboard, plastic wrap, and water bottles. Our initial design that we have come up with would mimic a platoon boat in that the water bottles would be contained in a net on two sides of a raft keeping it afloat. We are using these materials because they are easily assemble so if a disaster occurs such as a hurricane, people would be able to help themselves escape instead of helplessly waiting for someone else to come save them.
Subscribe to:
Posts (Atom)





